JEE Main 2024 Mathematics question — Arithmetic progression

A software company sets up mm number of computer systems to finish an assignment in 17 days. If 4 computer systems crashed on the start of the second day, 4 more computer systems crashed on the start of the third day and so on, then it took 8 more days to finish the assignment. The value of mm is equal to:

SOLUTION

We need to find the value of mm (number of computer systems) so that the assignment is completed in 25 days after crashes.

Total work = 17m17m system-days since mm systems would complete it in 17 days.

With 4 systems crashing at the start of each subsequent day:
Day 1: mm systems working
Day 2: m−4m - 4 systems
Day 3: m−8m - 8 systems
⋮\vdots
Day kk: m−4(k−1)m - 4(k-1) systems

The total work done in 25 days is ∑k=125[m−4(k−1)]=25m−4∑k=024k=25m−4⋅24×252=25m−1200\sum_{k=1}^{25}[m - 4(k-1)] = 25m - 4\sum_{k=0}^{24}k = 25m - 4 \cdot \frac{24 \times 25}{2} = 25m - 1200.

Setting this equal to the total work gives 25m−1200=17m25m - 1200 = 17m, so 8m=12008m = 1200 and thus m=150m = 150.

The correct answer is Option (1): 150.